The Importance of project closing
It is the process of finalising all activities for the project. The key benefits of this process are the project is closed, the planned work is completed, and project organiSational team resources are released to pursue new projects. After the project closing, the project will be commissioned by the Project Team and handed over to the Facilities Team.
Commissioning criteria pg 64
Installed properly into the building
Bought into operation successfully (known as 'start up' of systems)
Designed appropriately by the design team
Operate smoothly and satisfy the specified design
Activities during Project Closing Phase 62-63
Administrative closing of all procurements and contractual obligations.
Formally recognizing the completion of a project and its transition to operations. (Handover from PM to FM)
Reviewing the governance processes.
Validating that the project achieved benefits identified.
Validating and acceptance of deliverables. (Commissioning)
Disbanding project resources, freeing them to perform other projects.
Making sure all work have been completed.
Transitioning project deliverables to the customer organization. (if project is for sale)
Project Handover Documentation pg 65
Staff training and contract warranties
Statutory permits and certificate
Commissioning test result and record
Contractor's final account - Settle final progress claim after defect liability period (DLP)
Operation and maintenance manual
contractor's final account - Both structural and architectural and M&E as built drawings
Lists of defects - unfinished work etc
Building Asset Register - BIM project information that contains FM asset register and inventory
Project Commissioning pg 63
Commissioning is performed during the project closing phrase to validate prior to accepting the completed works or services.
Building commissioning is the systematic process of ensuring and documenting that all building systems perform according to specification and design intent, while also meeting the operational needs of the Client.
Types of building Services require commissioned -more on pg63
Heating and ventilation systems
Automated building controls systems
Air-conditioning systems
Automatic fire sprinkler systems
Security systems
Commissioning Parties(Team) pg 64
A specialist commissioning agent (CA) - for very large projects
The design team consultants (e.g. Architect, M&E Engineers)
The Main Contractor
The sub-contractors/vendors
The client's Project Manager (PM)
The equipment manufacturers
The client
The Client’s Operation & Maintenance Staff (e.g. The FM team)