Industrialised Building System
Overall Process (IBS Works)
Start
Design & Shop Drawing
Production Of Precast Component
Delivery
Installation
In-Situ/Wet Joint Works
Finish
What Is IBS?
A technique of construction where by components are
manufactured in a controlled environment
, either at site or off site,
placed and assembled
into construction works
Production Of IBS
Re bar Fabrication
Storage
Mould Preparation
Insert Steel Cage
Mould Fixing
Inspection
Concreting
Approved
Curing
1 more item...
Based On Production Order
Installation Of IBS
Start
Casting Yard Storage
Transport
Storage At Site (Nearest To The Installation Area)
Setting Out Marking & Level Checking
Install Precast Columns
Check & Grouting
Install Precast Beam
3 more items...
Disapproved
Rectify
Equipment & Machinery
Crawler Crane
RT Crane
Tower Crane
Trailer
Marking Column Position
Lifting Column
Positioning Column Through Starter Bar
Sealing The Gaps At The Bottom Of The Column
Grouting
Check