Highways
Lean Activities - Coggle Diagram
Highways
Lean Activities
A38
Lekha & Kris
Collab Planning
For Collaboration & Improved Comms Cell Production Control
- Map deliverables on Miro June-Oct
- 2 hour session with A38 design team
- Go through June-Oct P6 deliverables (up to Aug good enough)
- Populate tasks to complete each deliverable
- Map out week by week activities for each discipline
- Use each weeks activities for Tues Comms Cell call
- CP 1 hour session bi-monthly
- Benefit - to drive outputs & flag up support required on weekly Comms cell calls
Lekha & Sean
Design delivery strategy for SoW - March 2021 / Sept 2021
- Collab Planning session to map feasibility of Prog design outputs to ensure efficient delivery to meet SoW
SLCA
Completed for July 2020. Score = 2.0
- LCX (RS/KB/LG) - Requirement for CP in use
- Next SLCA in Sept 2020 for aim of 2.5 by end of 2020
Comms Cell
Improve weekly Comms Cell
- Use 8week look ahead from CP session to drive week by week outputs across disciplines
- Aim: to have structured forward looking tasks for discipline leads to update 15mins at start of call - Yes/No/If not why not with reason & flag up implications of delay
Lekha & Sean & Kris
-
A27
Lekha
-
CBA Decision Matrix
10 step process to investigate
options to quantify decision
- Activity 18 (w/c 20th)
- Activity 16 (w/c 27th)
PMO
Process maps -
Complete future state for following categories
- Efficiency registers - Neil
- Visual management - Paul
- Collaborative planning - Miguel
- Continuous improvement - Mike
- Production control - Lekha
Neil & Lekha
-
-
M54
Lekha & Kris
-
-
-
Unified method of actions, decision, risks
HELMA 2021
Lekha
SLCA across all Roads & Streets projects
- HE SLCA - M54, A27, M27
- SLCA across other HE projects
- SLCA across streets projects
Charter update with SMART measures
- Use to baseline & measure projs bi-annual Aug & Feb
Communicate Lean Strategy
- 3 slides to share Lean Strategy to Projs
- 1 slide for Rory to share Sept update
- Rory / Darren to email out to all Highways PMs & teams requirement to meet CI & Lean promises for delivery
Lean Policy Deployment Matrix (LPDM)
Update monthly - actions, support, projs
Efficiency Registers
- M54
- A46 Walsgrave
- A52 Nottingham
- A38 Derby
- M42 J6
-