Please enable JavaScript.
Coggle requires JavaScript to display documents.
TRA2020 V 1.5 - Coggle Diagram
TRA2020
V 1.5
1.0 Overhaul
1.6 commisssioning
1.5 Oil flush
1.4 Auxiliaries
1.3 J31320-T
1.3.1 Disassembly
1.3.3 reassembly
1.3.2 Inspection
1.2 J31320-C
1.2.1 Disassembly
1.2.3 reassembly
1.2.2 Inspection
1.1 Decommissioning
1.7 Closing
2.0 Preparation
2.2 Project management
2.2.3 HSE plan :star:
2.2.4 Quality plan :star:
2.2.2 Execution schedule[]2
2.2.6 Execution organisation (CV's and job descriptions) :star:
2.2.1 Risk Analysis :star:[]2
2.2.1.1 Safety risk analysis
2.2.1.2 Task risk analysis
2.2.5 Preparation plan :star:[]2
2.2.7 Project management plan
2.2.7.1 Scope baseline
2.2.7.2 Schedule baseline
2.2.7.3 cost baseline
2.1 Execution
2.1.5 Spare parts inspection report :star:[]1
2.1.4 Work packs
2.1.4.2 J31320-C
2.1.4.1 J31320-T[]3
2.1.3 Work permit requests :star:
2.1.2 Logistics plan
2.1.2.4 Personeel transport plan
2.1.2.3 Temporary facilities layout :star:
2.1.2.3.1 Tool container
2.1.2.3.2 Office and changing rooms
2.1.2.2 Platform setup[]2
2.1.2.2.1 Scaffolding
2.1.2.2.2 Tools
2.1.2.2.3 Utilities
2.1.2.1 Transport and cranage plan :star:[]1
2.1.1 Execution plan
2.1.1.4 Oil flushing plan
2.1.1.3 Workshop work plan
2.1.1.2 Team preparation plan
2.1.1.1 Commissioning plan[]1
2.3 Platform preparation