Resource-constrained project, Time-constrained project, Heuristics,…
-
-
Time-constrained project
-
-
Use positive slack (delaying noncritical activities) to manage resource utilization over the duration of the project.
-
Leveling
Techniques used to examine a project for an unbalanced use of resources, and for resolving resource overallocations.
-
Resource smoothing
Involves attempting to even out varying demands on resources by using slack (delaying noncritical activities) to manage resource utilization when resources are adequate over the life of the project.
-
-