Start Up Process (Infrastructure (• Check all controls on boilers and…
Start Up Process
Infrastructure
-
-
• Start water system 24 hours prior and get chemical levels correct. Order filters and change often the first few days.
• Verify that we have no accumulation of water in steam header prior to starting machines. This could cause excessive water hammer and damage line or presses.
• Verify we have no new air, water or steam leaks while being down.
• Open valves on bottom of receiver tanks until no water comes out and crack bleed off valves on compressors.
-
-
• Grease all tie bars, telescopes, and KO board guide bars.
-
-
-
• If oilers are present insure, they are full.
-
-
• Start boilers very slow. We need to verify boiler never comes off low fire until it is up to operating pressure.
-
-
-
-
-
-