Road Construction (Pavement Works (Subbase (Material: Sand, Gravel,…
Road Construction
Pavement Works
Subbase
Material: Sand, Gravel, Crushed aggregate, Clay lumps
Compaction in longitudinal direction, lower edge towards crown, density>=95% MDD
-
Pavement Works
Surfacing
-
-
Surface Layer:
- Binder course layer is laid on the road base after it is cleaned and sprayed with prime coat.
- Lay in dry condition.
- Tack coat is sprayed on top of binder course layer before wearing course layer and compacted.
- Mixture of bituminous material must fulfill specifications.
- Aggregate quality: ACv<30, Soundness<12%, FI<30, WA<2%,coating>95%
-
-
Pavement Works
Coating
Prime Coat
Liquid bitumen, sprayed into clean inbound roadbase
-
MC-70 (50-70C), SS-1K (25-45C)
Curing: 24 hrs
Tack Coat
Bitumen emulsion, sprayed onto bituminous layer
-
-
-