Topic 6
Excavation (Purpose)
Stripping
Removal of all material between the original surface and the top of any material that is acceptable for permanent embankment
-
Roadway excavation
Portion of a highway cut that begins where stripping was completed and terminates at the line of finished bottom of base course called subgrade
Pit / Hole excavation
Digging of a column or pile cap foundation for building, manholes and inspection chamber for deep sewer connections
Backactor for excavating a pit or shallow basement.If the pit is very deep, and the soil is wet, a grab would be needed
-
-
Excavation (Soil Types)
Top soil Excavation
Removal of the exposed layer of earth's surface, removing all vegetation
-
-
-
-
Unclassified Excavation
Removal of topsoil, earth and rock
-
-
-
-
-