How to improve productivity? (Coordination (Identify, materials and tools…
How to improve productivity?
Coordination
Identify, materials and tools to execute the work
Specify tools and consumables needed for the microplanning
:silhouette: Alejandro 10-jan
Coordination with other areas
Design a production meeting between aluminum, steel and logistics teams to review the current week, W-1, and W+1
:silhouettes: Lean Team, Melinda Menou and Pablo Lagun 13-jan
Preparation of necessary machinery
Specify materials and machinery needed for the microplanning
:silhouette: Marlene Rodrigues 10-jan
Design a method to bring down information to the field
Create a daily meeting for the distribution of tasks by supervisor and his group
:silhouettes: Lean Team, Vitor Santos and Pablo Lagun 13-jan
Establish tasks to be carried out on a weekly or daily basis, defining who makes what
Establishment of a weekly microplanning (weekly and daily tasks)
:silhouettes: Pablo Lagun and Vitor Santos 8-jan
Quality
Verify quality of work before calling QA
Analyze resource availability for quality review on all fronts
IN PROGRESS FACADE TEAM
Avoid rework, do well at first
Generate a quality control before being reviewed (pre quality)
:silhouettes: Pablo Lagun and Vitor Santos 13-jan
Logistic and warehouse
Facade materials are received in the general warehouse
Review flow of reception for facade materials in the warehouse
:silhouette: Stephane Chaing 19-dec
Tool maintenance generates low availability
Review maintenance plan and tool replacement
:silhouette: Stephane Chaing 19-dec
Some suppliers send materials with dimensions other than those encoded. Identifying these variations in the execution of the works
Propose improvements to the process of receiving materials from unreliable suppliers
:silhouettes: Lean Team 27-dec
Identify the materials we have at work due to the lack of trust in the supplier
Review of materials available at CJV for pilot week
:silhouette: Marlene Rodrigues 10-jan
Safety
High frequency of AST generation for repetitive tasks creating waiting time before starting the activities.
Manage the feasibility of performing weekly AST
:silhouettes: Lean Team 18-dec