Project Management Process
Preliminary Brief with Client
1.1 Analysis Function
1.2 Preliminary Design
1.2.1 Design Layout Plan
1.2.2 Section Plan
1.2.3 Elevation Plan
1.3 Material Approve
1.4 Cost Control
1.5 Time Schedule
1.6 Pre-Production Process
2 Presenting to Client
2.1 Reject
2.2 Revise
2.3 Sign Contact
Design Development
3.3 Material Approve
3.4 Cost Control
3.5 Time Schedule
3.6 Design Calculation
3.7 Shop Drawing
3.8 Order Material
3.0 Drawing
3.0.1 Construction Permission Drawing
3D Model
Drawing
Calculashion Sheet
3.0.2 Shop Drawing
3.0.3 Light Gauge Shop Drawing
3.0.4 Erection Drawing
Production Process
4.1 เหล็กรูปประพันธ์
4.1.1 Cutting
4.1.2 Items Marking
4.1.3 Pre-Assembly
4.1.4 Small Plate Welding
4.1.5 Blasting
4.1.6 Painting
Paint
4.1.6.1 Normal Painting
Primer
Top Coat
Fire Proof Painting
4.1.6.2 Hot Dip Galvanize
4.2 Hot Rolled Plate
4.2.1 Cleat
Cutting
Marking
Drilling
4.2.2 Beam
Cutting
Welding
2.1 Track Welding
2.2 Butt/Submerge Welding
Straightening
Fixing / Grinding
Items Marking
Pre-Assembly
QC Approve
Blasting
Painting
Normal Painting
Fire Proof Painting
Primer
Top Coat
Hot Dip Galvanize
Quality Control
Produce Report
Produce Warranty Certificate
Packing
Shipping
4.2.3 Jig
1 Cutting
Drilling
Construction
5.1 Preliminary Site Check
5.2 Crane Calculation
5.3 Items Arrived
5.4 65-70% of Last Payment
5.5 Set up