COST MANAGEMENT

Overview

Plan cost Management process

Cost management plan

Life cycle costing

Value Engineering

Estimate Costs process

Types of Cost (4 mains)

Estimating

Inputs to estimating cost

Determine budget process

Accuracy of estimates

Project budget components

Control cost process

Progress reporting

Earned value management

Definition: Process required to complete the project in which the approve budget

Major Output

Project budget (cost baseline)

Primarily concerns with the cost of resources need to complete project activities

Cost management process

Plan cost management

Estimate cost - Planning

Determine budget - planning

Control costs - Monitoring & controlling

Establishing policies, procedure, and documentation for planning, expending and controlling project costs

Provide guidance and direction on how the project costs will be managed throughout the process

Major output: Cost management plan

How will i go about planning cost for th eproject

How will I manage the project to the cost baseline

Part of project management pln

Cost management plan includes

Unit of measure

Level of precision - rounding up or down

Control thresholds

Rules of performance measurement (EVP technique)

Reporting format

Additional deteails

looking at the cost of whole life of product, not just the cost of product in the project

Finding less costly way of the same work

if team is devreasing costs with same scope, they are performing value analysis

Process of developing an approximation of the monetary resources needed to complete project activities

Estimate for each activities are done

Dertermines the amount of cost required to complete project work

Costs are estimated for all resoures that will be charged to the project - labor, materials, equipment,...

Estimation costs are similar to estimating done in time management

Recap - important points about estimateting

Should be based on WBS improve accuracy

ETA of an activity should be done by the person doing the work

Historical information from past projects is key

Cost baseline should be taken in the beginning and should not be changed except change request

Chnages should be requested when cost problem occur

Project manager may periodically recalculate the estimate to complet

There is a process fro creating the most accurate eta

PM must meet any agreed upon ETA

ETA can be decreased by reducing the risks

Cost of all work needed to complete the project is ETA including

cost of quality efforts

cot of risk effort

cost of project manager's time

Cost of project managemet activities

Cost directly associated with project - trainig, paper, pencils

cost of office expenses

profit when applicable

Overhead costs - management salaries, general office expenses

Variable Costs: Costs change with amount of Production/ work - Wages, material

Fixed cost: do not change as production change- set up cost and rental cost

Direct costs: Direct attributable to the work on project - wages, materials

In deric cost: Overhead item or costs incurred for the benific of more than one project - taxt, security of company

Scope baseline

Project schedule

Timing of somthing you buy affects its cost

you need to develop a time phased spending plan

Human Resource Plan

Rewards, Labor rates, qualifications, quality

Risk register

Risks are input & output for ETA costs process

Cost for risk control

Policies on ETA templates, process, procedures, lessons learned and historical infor

Company culture and existing systems

Project management costs

Effort of project manager, status report,..

Tools and technique used in estimate activity duaration process can be used in estimate costs process as well

One point ETA

Analogus estimating

Parametric ETA

3 point ETA

A new technique for cost ETA

Bottom up ETA

  1. Detailed ETA is done for each activities or work package
  1. ETA are rolled up to control accounts
  1. Then into overall project ETA

Require an accurate WBS

ETA in early phase of a project are less than those made later in the project

ETA must be in a range

Ranges are wider in the beginning of the project and will narrow as more information is dertermined during project

ROM- Rough Order of Magnitude

Usually made in initiating

Budget ETA

25%- 75% for actual

Usually made in planning

In the range of 10 % to 25% from actual

Definitive ETA

Later during the project, ETA will become more refinied

Range +_ 10 % or 5%

Process of arregating the estimated costs of individual activities or work packages to establish an authorized cost baseline

Determine the cost baseline

Budget = total cost of the project

Budget defines how much mony need to prepare during the project

Project estimate canot completed without risk management activities and the inclusion of reserves

Contingency reserves: to address the cost impacts of remaining risks

Management Reservers: to address the cost of any unforeseen risks or changes