Technical Mtg 07.01.21
Shipping program
10 containers/Day
Safety
Jorge Ibarra
Safety of people
COVID 19
Patrimonial safety
Perimetral Fence
Provisional electricity line CFE
Logistics
Coordination
Documents
Javier Alonso
Materials Warehouse
Building 2,000 m2 warehouse
Last meeting 03.12.20
Expansion joint between GH and Packing
Digging plan
Next week
Suppliers Meeting
DLV
Additional purchases to PRINS
Order modification
Glass, Screens & Insect Netting
Growers Academy Design
Foundation
Prins inspectors (2 W stay)
Pin pionting of the project
Hole digging
Installation of foundation pins
Packing Facility
Foundation 60%
Building of the structure
Design of packing process / Quotations
High Way acces
piping of irrigation channel 60%
Trees relocation
Entrance ramp
Platforms
Packing 100%
2B 70%
AGENDA
Construction actualization
Grower´s Academy design
Safety Program
Digging Plan