deepwater-horizon-1280x640

Event sequence 20/04/2010 (CNN, 2010)

System parts

12:35am - Cement contractor, Halliburton, completes cementing in well

11:00am - Meeting between BP and Transocean executive management regarding changes in drill plan

5:05pm - Unexpected loss of fluid in riser pipe, suggestive of leaks in blowout preventer

5:00-7:00pm - Negative pressure tests run. Results are indicative of leaking and a build up a natural gas.

8:00pm - Testing ends and remaining drill fluids replaced with seawater

9:00pm - Reports indicate more fluid is flowing out of well, then being pumped in

9:10pm - Well pipe shutdown, well continues to flow and drill pipe pressure increases

9:30pm - Increased fluid and abnormal pressure observew. Well pip abruptly shudown

9:50pm - Gas surge and drilling fluid observed to be onto deck. First explosion occurs.

9:52pm - Distress call issued and order given to abandon rig.

People

Workplaces

Management

Workplace factors

Site design

Fixed plant

Geotech design

Access

Equipment design

Work environment

126 people on the rig at the time of the accident, 11 killed (CNN, 2010)

The rig had six large diesel generators powered by onboard electric plant, and a smaller back up diesel generator (National Academies Press, 2012)

Maconda well had a total depth of 18,300ft below sea level and in more than 5,000 ft of seawater (National Academies Press, 2012)

The rig was a self-propelled vessel and stable floating base used for drilling and construction of an undersea well (National Academies Press, 2012).

The rig's design accommodates propulsion power to ensure the stability of the site against wind and ocean currents (National Academies Press, 2012)

Protective electrical and mechanical devices were installed to detect combustible gas and prevent ignition, in areas where explosive mixtures of hydrocarbons and air may accumulate if released (National Academies Press, 2012)

Three overspeed shutdown devices were fitted, however none were designed to shutdown air intake to engines directly (National Academies Press, 2012)

System did not determine that the diesel engine was 13% above rated speed (National Academies Press, 2012)

Warning systems

Integrated Alarm and Control System (IACS) controlled and monitored the rig alarm system (National Academies Press, 2012)

27 Combustible Gas Detectors (CGDs) on the rig. 13 of which were able to secure ventiliation fans and electrical power to an affected area. 14 had just an audible and visual display (National Academies Press, 2012)

The CGD in the engine rom did not have an automated response and required a crew member to validate the alarm and then take manual actions (National Academies Press, 2012)

Accident occurred at night - darkness, no power (CNN, 2010)

Fumes and risk of inhalation of oil and gas after surge and spill onto rig deck (CNN, 2010)

Blowout Preventor (BOP) installed as a means of well control to seal an open well bore, close the annular portion of the well, or cut through the pipe and then seal the well (National Academies Press, 2012)

BP deferred maintenance of the upper and lower annular of the BOP less than a week before the accident (National Academies Press, 2012)

Significant fire on the rig (National Academies Press, 2012)

BOP not designed for dynamic conditions in existence at the time and determined not to be a high-reliability, fail-safe device based on design, test, operation and maintenance (National Academies Press, 2012)

The rig is located 114 miles from Port Fourchon, Louisiana, and 154 iles from the Houma, Louisiana, helicopter base (BP, 2010)

Access via helicopter/boat

Staff were employed by BP, Halliburton, and Transocean (BP, 2010)

Organisational/system factors

Drilling team mistakenly determined the cementing operation had been completed successfully, and conducted a negative pressure test (National Academies Press, 2012)

Drilling team mistakenly determined the negative pressure test had been conducted successfully, and subsequently abandoned the well (National Academies Press, 2012)

Decision made to displace the drilling mud with seawater despite failing to demonstrate integrity of the cement and negative pressure tests (National Academies Press, 2012)

Emergency Disconnect System (EDS) failed to operate as it required manual activation - impacted due to fire on rig floor (National Academies Press, 2012)

Blowout of Macondo well (National Academies Press, 2012)

Gas hydrocarbons released, in conjunction with low wind velocity made ignition inevitable

Lack of strong safety culture (National Academies Press, 2012)

Lack of appropriate policies and procedures that provided an effective system safety approach applicable to the Macondo well (National Academies Press, 2012)

Geologic conditions posed challenges to the drilling team

The training of management and decision makers both in industry and the regulator was inconsistent with the level of complexity and risks associated with deepwater drilling (National Academies Press, 2012)

Schlumberger team responsible for performing full analysis of geological safety of the well was denied ability to perform Cement Bond Log (CBL), and to have kill fluid dumped down well (EDM Digest, 2017)

Transocean and BP staff misinterpreted results of negative pressure tests (EDM Digest, 2017)

No fixed fire-extinguishing system installed on Drill Floor and adjacent areas (EDM Digest, 2017)

Drilling crew failed to use the diverter line for well flow, instead of the MGS - this caused gas to discharge on the main deck (US Coastguard, 2011)

Lack of systems to track hazardous electrical equipment - some on board were in bad condition and corroded, and left in hazardous areas. This created a potential cause of the explosions (US Coastguard, 2011)

Bridge crew was not provided training on activation of the Emergency Shutdown (ESD) system (US Coastguard, 2011)

Procedures on emergency shutdown system not provided to responsible staff - this could have prevented or delayed explosions (US Coastguard, 2011)

Some gas detectors were bypassed or inoperable at the time of the explosions (US Coastguard, 2011)

The rig lacked appropriate crew blast protection against explosion (US Coastguard, 2011)

Information Transfer

No transfer of authority occurred after explosions causing confusion at a critical point of the emergency and possibly impacted the activation of the emergency shutdown system (US Coastguard, 2011)

External factors

click to edit

Software

Humans

Halliburton

BP

click to edit

Transocean staff had not had sufficient training to take full responsibility for the safety of the vessel (US Coastguard, 2011)

Transocean

Crane Operators

Assistant Drillers

Floorhands

Derrick Hands

Chief Mechanic

Roustabouts

Assistant Engineers

Motor Operators

Division Manager

Chief Electronics Technician

Staff responsible for cementing the well

Executives

Mechanics

Ocean currents

Water pressure

Weather

Gas detectors

Fire detection and protection systems

Diesel generators

Drill pump

Emergency shutdown system

Fire main system

Toolpushers

Cranes

Propulsion thrusters

Drilling Team

Executive Management

click to edit

Human/machine interface

Emergency shutdown system

Dynamic Postioning console

Navigation System

Power and vessel management system panel

Load and stability computer system

Drilling deck console

Driller's intercom

Blowout preventer control panel

Drilling equipment control system

Uninterruptible power supple and charger/battery system

Drilling drive power systems

Electric power plant

Blowout Preventor

Thruster drive power systems

Visual and audio alarms

Water and weather tight doors

Lifesaving appliances

System Lifecycle

Concept

Construction

Commissioning

Operating

Maintenance

Decommissioning

Drilling deep sea to extract oil for petroleum from beneath the seabed

Risks to human life from drilling proess

Risks to ecological life due to oil and gas related factors

Built by Hyundai Heavy Industries - commenced construction 1998, completed in 1991 (US Coastguard, 2011)

Commissioned by R&B Falcon, which became part of Transocean (US Coastguard, 2011)

Electrical equipment installed may not have been capable of preventing ignition of flammable gas (US Coastguard, 2011)

Fire and gas detection systems installed did not automatically activate emergency shutdown system (US Coastguard, 2011)

Regulatory factors were considered to be insufficient as they did not cover several specific aspects that may have changed the course of the outcome - International Maritime Organisation (IMO) Mobile Offshore Drilling Unit (MODU) Code

Appropriate blast protection not installed (US Coastguard, 2011)

Arrangement of air inlets was not taken into adequate account - flammable gas may have affected all engine rooms due to this (US Coastguard, 2011)

Incorrect labelling of type of vessel determined implementation of type of management structure causing on who is responsible for emergency shut down

Appropriate training and trained crew required for operation of rig (US Coastguard, 2011)

Appropriate organisational structure required (US Coastguard, 2011)

Rig was incorrected listed as a self-propelled MODU which caused incorrect organisational structure to be implemented, resulting in possible lack of appropriate training being provided for emergency shut down (US Coastguard, 2011)

A-class fire barriers installed were not effective in preventing spread of fire (US Coastguard, 2011)

No consideration given to attempting to account for condition and location of crew members prior to abandonment of ship (US Coastguard, 2011)

Schedule maintenance required by appropriately trained mechanical staff

Adhoc related maintenance required as a result of audit findings by appropriately trained staff

Project Management (Rigzone, 2019)

Significant cost - on average $4-10 million (Rigzone, 2019)

Permitting and Regulatory Compliance (Rigzone, 2019)

Review contractual obligations

Engineering analysis

Operational planning

Contracting, often times 2 years in advance

Obtain permit to decommission - can take up to 3 years

Execution plan required for schedule of decommissioning activities

Permits required from Federal, State and local regulatory authorities

Platform preparation (Rigzone, 2019)

Tanks, processing equipment and piping to be flushed

Residual hydrocarbons disposed of

Platform equipment to be removed

Divers to prepare underwater removal

Well plugging and abandonment (Rigzone, 2019)

click to edit

Well abandonment

Planning

Preliminary inspections

Determine abandonment method

Submit application for Bureau of Ocean Energy Management, Regulation and Enforcement (BOEMRE) approval

Data collection

Well entry preparations

Slick line unit use

Filling well with fluid

Removal of downhole equipment

Plugging bottom of well, casing stubs, annular space

cleaning out wellbore

Placement of surface plug and fluid between plugs

Conductor removal (Rigzone, 2019)

Mobilisation/demobilisation and platform removal (Rigzone, 2019)

Pipeline and power cable decommissioning (Rigzone, 2019)

Material disposal and site clearance (Rigzone, 2019)