Retrospective
Mar 25 - Apr 5
(Sprint 37)
What went well?
We have utilized our time very well by participating in reviews and focusing on task
We kept speed with the previous sprint with regards to points
Whenever a PR is created the author notifies everyone for immediate review
We did our evaluation and sets our individual target
We met the MVPs from ID, TH, and VN
Integration test and unit test was added for features that doesn't have it yet
What actions are needed?
Focus on reviewing big point task
If task has a big point, target to finish it in the first week of the sprint
Every member should notify the members whenever a PR/review fix was finished
Local testing should be confirmed before giving LGTM
take time to check the cards' contents and the feature to modify carefully before the grooming sessions to find problems with the ACs
split cards between team members to check before grooming sessions
What needs improvement?
There is still a problem with cloudfront edge server
Big task took too much time
There are task that took too much time from review phase to merge
Many tasks were carried to the next sprint
No notification was sent to the members before syncing of data from production to dev
Performance of laptops are low
There are some bug found during staging test that was not found during reviews