OMSMAF Website Development (Development (Dev) (Business Analysis…
OMSMAF
Website
Development
Development
(Dev)
Test
Stage 5
Testing the Product
Stage Server
Prevent Scope Creep
Hotfix vs feature
Product defects are reported, tracked, fixed and retested, until the product reaches the quality standards defined in Step 2.
Test Server
High Fidelity: Functionality Sign-off
Build / Test
Stage 4
Building or Developing the Product
High Fidelity
: Development starts and the product is built
Developers follow the best practice guidelines
Collaborate with Stephan's team. Linking logged out with logged in portal.
Portal skinning and branding
Design
Stage 3
Designing the Product Architecture
Proposed product architecture reviewed by stakeholders - the best design approach is selected for the product
Low Fidelity
: Design of modules of the proposed architecture should be clearly defined
INFORMATION ARCHITECTURE
and
CONTENT
Development
IA and Content Sign-off
Business Analysis
Stage 1
Planning & Requirement Analysis
Basic project approach, product feasibility study, operational and technical areas
Quality assurance requirements, Identification of risks associated with the project
Stage 2
Defining Requirements
Define and document product requirements to be designed and developed
Scope/Brief
Input from the customer, sales department, market surveys, domain experts in industry
Operations
(Ops)
Stage 6
Deployment in the Market and Maintenance
Release
Product released and tested in the real business environment
Monitor
Monitoring of availability and functionality, (verify service level agreements)
Identification of problems
Problem Resolution
Diagnosis and resolution of problems
Operations
Support
Web Dev
Maintenance
Done for the existing customer base
4 Weeks
April
Low Fidelity
Sign-off by: 30 April
6 Weeks
1 May - 14 June
High Fidelity
: Design Sign-off
2 Weeks
17 - 28 June
Release = 1 July
.
2 Weeks
Stage 6 = 1 - 12 July
Release = 1 July
Week 1:
1-5 April
Week 2:
8-12 April
Week 3-4:
15-26 April
Team Resources: Website Developer,
Digital Designer,
Copywriter
Project Starts:
1 April 2019