Chapter 6 (milestone (features (Specific, Measurable, Assignable,…
Chapter 6
milestone
is a significant event that normally has no duration
features
Specific
Measurable
Assignable
Realistic
Time-framed
Duration estimate
What are they?
optimistic
most likely(middle)
pessimistic estimate
important
look at chapter 6 page 49
Project time management
main processes
Planning schedule management
Defining activities
Sequencing activities
Estimating activity resources
Developing the schedule
Controlling the schedule
Activity definition
main features
the activity name
activity identifier or number
a brief description of the activity
Dependencies
types
Mandatory dependencies
Discretionary dependencies
External dependencies
critical path
look at
important
chapter 6 slide 58
task dependency type
what are?
important