Retrospective Dec 3 - Dec 14 (Sprint 29) (What went well? (Tracking…
Retrospective
Dec 3 - Dec 14
(Sprint 29)
What went well?
Tracking system training successful
Clean code training was very useful
No immediate health problems in the team!
Training skill of a member has increased
Hired new member in Tokyo (from Feb.)!
New alert for ECS issues
TH achieved their financial goals in the last 2 months
Good communication between dev team and TH team
What needs improvement?
Couldn't deliver as many points as usual
Missed a bug before creating the pull requests for a task
Some product feed downloads are still failing
Internal problems in ECS
Didn't notice breaking change about S3 bucket names until publishers notified us
What actions are needed?
Fix MongoDB sync batch so jar file doesn't get broken
Everyone should be careful about their health
We should work on dependent tasks in order