SONG HAU PLANT 1 (II (Coal Handling System of Song Hau 1 includes: (Coal…
SONG HAU PLANT 1
II
Quantity for testing and commissioning for Song Hau 1 Plant
Design 1,200,000 Ton
Performance 200,000 Ton
Total 1,400,000 Ton
Timing of receiving coal:
The items/work of the Song Hau plant shall be readily completed for receiving coal in May 2019
Time of receiving coal for testing and commissioning:
expected in Dec 2019
Coal Handling System of Song Hau 1 includes:
1 Coal Berth:
Coal unloading system on the berth with 02 chainbucket ship unloaders with capacity 850 ton/hour/machine(max)
Conveyors, transfer tower; coal yard is designed semi--closed, with capacity of 30 days of full load and can extend to 45 days (including 3 storage); and other equipment(stacker-reclaimer, bulldozer and auxiliaries.
center storage with capacity of 1 x 150,000 ton
side storage with capacity of 2 x 102,000 tons
Coal unloading berth is designed with 1 overhang berth on Hau River with basic parameter:
Berth L 310m W 25m
High top dock 3.5m
high bottom dock -11.85m
high water level elevation design + 2.24m
high level design -1.77m
approach bridge 1: L 72m W 6m
Information for proposal of suppliers:
Price and delivery terms: CIF at discharge port/Coal Jetty of SH1(incoterms, edition 2010) and whole of related fees such as: freight, insurance, cost of wastage and administration fees
III CHANNEL INFORMATION AND LOCATION OF DISCHARGING TRANSSHIPMENT
Channel Information