Capital Redeployment measures if it’s worthwhile to continue a scrum project, or if the economic value of the project now exceeds its costs. In this case the team should be redeployed to other, more profitable projects.
To determine Capital Redeployment, calculate the revenue value of the remaining items in the project backlog (V), the actual cost (AC) of the sprints needed to complete those items, and the opportunity cost (OC) of alternative product work the team could do. When V < AC + OC, the project should end and the team redeployed to other projects.