ACSM case study, Production of glass vials?, This should be done with…
ACSM case study
High level risk scoring methodology
regulatory
Labor unrest
Environmental incidents
Other risk?
financial
Other risk?
Suppliers that pose the most risk?
Problems faced by suppliers
Operational challenges.
Marketing team has insights on anticipated demand trends for various SKUs
Understand obsolete inventory
Plant in Switzerland, GlasWork - Most critical
Estimate the change in inventory position to understand the working capital impact.
Identify if there is any capacity constraint for Fabricadas- new facility in Chicago.
Plant controller thinks it is not adequate capacity but VP believes otherwise. Decision? explain? Recommendations?
Review Mitigation Activities
Recommend how to maximize utilization to meet demand.
Production of glass vials?
This should be done with without distorting production other products.
Production capacity -8 billion per year
requirement - 2 billions for Covid 19 global immunization drive- for Payima Biotec