Outcome 4: NAP formulated and capacity for implementation and monitoring established USD 275,768.8

4.1 NAP formulated Plan formulated and communicated

4.1.1 Constitute a multi-disciplinary team to draft NAPs

4.1.2 Constitute a peer review group and advisory group

4.1.3 Organize consultation meetings at the national and subnational level in collaboration with MRG

4.1.4 Prepare a draft NAP including implementation & financing strategy

4.1.5 Final draft NAP reviewed and approved by the C4 and NCCC.

4.2 Strategy for NAP implementation developed

4.2.1 Develop a medium term NAP implementation strategy as part of the NAP

4.3 Outreach on the NAP process and report on progress and effectiveness developed

4.3.1 A NAP national launch workshop will be organized to communicate and disseminate the NAP to all stakeholders

4.3.2 Annual consultation workshop will be held to share information on the progress in the formulation and implementation of the NAP

4.4 System to report, monitor and review the NAP process established

4.4.1 Develop a M&E framework for assessing "climate resilience" to inform and assist integration of CC adaptation into development planning

4.4.2 Develop and integrate a monitoring and evaluation (M&E program for the implementation of the NAP process

4.4.3 Based on the NAP M&E framework, prepare an Annual NAP implementation progress to include assessment of NAP progress, effectiveness and gaps

4.4.4 Adaptation criteria to be developed and applied within the government performance management system to report on adaptation relevant investments and expenditure.

ToR drafted for team

Y1, Month 10-12

Selection criteria developed for team members

Y1, Month 10-12

Report formulated

Y2, Month 20

Draft a NAP

Y3, Month 25-27

NAP document finalized

Y3, Month 36

Report of implementation strategy developed

Y4, Month 37-39

Workshop organized, NAP submission to UNFCCC

Y4, Month 37-39

4 workshops in Q3/4 of each year

Y2,3,4

M&E framework with an index and set of indicators for resilience to CC impacts developed

Y4, Month 40-48

M&E protocol for assessing progress, effectiveness and gaps in the NAP process after tools in Outcomes 1&2 are completed

Y4

Annual NAP implementation progress report

Y4, Month 44,45

Criteria prepared and agreed with Finance Departments and line agencies

Y3, Month 32-48