Progress Theme (Event-driven Controls (Creation of an Exception Report,…
Progress Theme
-
-
Work Package
Used to pass responsibility to a Team Manager or Team Member for the production of one or more products**
-
-
-
Tolerance
Permissable deviation allowed above or below a plan's target for Time and Cost without escalating to next level of management*
-
-
-
Supports Manage by Exception principle by only escalating to the next level of management when a deviation beyond agreed tolerances is forecast**
All levels on management use mechanisms included within the theme to control unacceptable deviations
-
Corportate, Programme Management or Customer set project-level tolerances*