Hopper Wash Facility WBS (1.3 Execution (1.3.1 Project Kickoff Meeting, 1…
Hopper Wash Facility WBS
1.2 Planning
1.2.1 Create Preliminary Scope Statement
1.2.2 Determine Project Team
1.2.3 Project Team Kickoff Meeting
1.2.4 Develop Project Execution Plan
1.2.5 Submit Project Execution Plan
1.2.6 Milestone: Project Execution Plan Approved
1.2.7 Management of Change
1.1 Initiation
1.1.2 Develop Project Brief
1.1.3 Deliverable Submit Project Brief
1.1.4 Project Sponsor Reviews Project Brief
1.1.5 Project Brief Signed/Approved
1.1.1 Evaluation & Recommendation
1.3 Execution
1.3.1 Project Kickoff Meeting
1.3.2 Verify & Validate User Requirements
1.3.3 Design Hopper Wash Facility
1.3.4 Procurement
1.3.5 Construction of Temporary Facility
1.3.6 Testing of Temporary Facility
1.3.7 Construction of Hopper Wash Facility
1.3.8 SOP and User Training
1.3.9 Go Live
1.4 Control
1.4.1 Project Management
1.4.2 Project Status Meetings
1.4.3 Risk Management
1.4.4 Update Project Management Plan
1.5 Closeout
1.5.1 Audit Procurement
1.5.2 Document Lessons Learned
1.5.3 Update As-builds/Records
1.5.4 Gain Formal Acceptance
1.5.5 Archive Documents