OCTA Ellipse 8.9 Upgrade
Schedule
Dev Setup
22-Dec-17
Prod Setup
9-Jan-18
DR, Tst, Train Setup
15-Jan-18
Go-live
19-Mar-18
Customer Acceptance Test
6-Feb-18
Tasks
Dev Setup
Finalization
8-Jan-18
Handover to OCTA
22-Dec-17
Create Resource Group
18-Dec-17
Build DB
20-Dec-17
Build Ellipse
21-Dec-17
Customer Acceptance
12-Jan-18
Prod Setup
Create Resource Group
19-Dec-17
Build DB
8-Jan-18
Build Ellipse
9-Jan-18
Handover to OCTA
9-Jan-18
Finalization
10-Jan-18
Customer Acceptance
6-Feb-18
Risks
Resource constraints
Scope
Upgrade Ellipse to 8.9
Dev
Test
Train
DR