PoC (Detailed Requirement gathering (Create survey email to confirm…
PoC
Detailed Requirement gathering
Create survey email to confirm requirements
Talk to the Comms people and confirm a comms plan
Email the CRMs, introduce BA and tell them about survey coming next
Email to users introducing BA and letting them know about survey coming out
send pilot survey out by Dec 19
send full survey out Jan 2
Create Detailed Requirements doc for approval
Internal workshops with Sasan, Chris and Rob to review current detailed requirements
Get Microsoft quote approved
MS starts jan 8
Discovery workshops - complete by Jan 20
HLD - complete by Feb 1
DLD - complete by Feb 1
Build PoC by feb 15
Technical testing (Rob, Chris) - Feb 15 - 28
updated PoC if required
User story testing - Feb 15-28
Migration testing with MS - Feb 15- 28
Migration plan
Find collocation space (which building?)