Discrete Maths (Scheduling (Activity Network (Critical Paths (critical…
Discrete Maths
Scheduling
Activity Network
-
-
Critical Paths
critical activity ESi=LSi, EFi=LFi
-
there can be multiple critical paths, and critical activities are not necessary to be on the critical path
critical activity has a total float of 0 #
-
Total Float
accumulated time which is free in the sense that not starting the activity in the time will not lead to a delay
-
-