what design schedules to DM's
stage 0; proposal stage Use execution flow diagrams. Create TP's
stage 2: Integrated planning w/shop (IPW)
planning
L1 schedule
Need: TM on creating design scheduels for DMs
resources planning
schedule logic / sequence
milestones
overall generic design flow
Need: tool: generic schedule template for stage 2
CM / KC
stage 3
IPW
L2 schedule
SBS
Need: Tool: generic schedule template for stage 3
CM/KC
lack of CM - say not appointed
construction schedule communication innovation adapted for design ie story boards
milestones
Tool: fragnets
stage 4
L3 schedule
method: last planner
needs tools, processes, TMs
construction schedule communication innovation adapted for design ie story boards
milestones
tool: fragnets
stage 1
level 1 by the PM
stage 5
new approach: DM to manage submittals?