MOTF Design (Floor steel to steel connections (L3- L4 (Calc to be approved…
MOTF Design
Floor steel to steel connections
L1
DWG & Cal approved
L1 M to L2
Revised calc 17 & dwg submitted. BHE to approve
Approved
L3- L4
Calc to be approved 24
Dwg approved
L5 to L7
BP 26
90 mm above
Maffeis to recheck
Upper part released
Mr.Ramesh posa to hold
go ahead
Node connections
L1 to L2(truss nodes covered)
BHE to approve Revised Calc and Dwg
Approved
L3 to L7
Calc & Dwg Approved
EVS to resubmit
Truss to diagrid connections
L3 to L4
EVS to submit
L5 to L7
EVS to submit
Spiral stair
JNM modeling Arun to raise RFI
Future stair
JNM modeling Arun to raise rfi
Stair 3
Maffeis to design one stair flight
Auditorium
Completed
Pantomimic lift hold Members/ set out not finalized
EVS to arrange alternate supporting detail
Reply to letter
Concrete connections
shuttle lift BAM to provide details