LatAm Datacentre Migration (Governance (Lessons Learned (EDB Engagement,…
LatAm Datacentre
Migration
Pre-Prod
Provisioning
wHost environment
Networking
Testing
OAT
Performance
Penetration testing
Externally facing
Size
Performant
Scaled env
Requirements
Test/Dev
Self serving environment
Decommission
Cost
Date
Current DC lease dates
Governance
Resource
Cost/Finance
Documentation
Risk/Issues
Timeline
Meetings... Stand-Ups?
Lessons Learned
EDB Engagement
Budgeting
Co-Location
Design
Pre-Prod amendments to plan
Service Transition
Patching Cycle
Deployment/Release Cycle
DR Mitigation
ITSM Integration
EDB Incident Management
Worldpay Incident Management
Worldpay Change Management
EDB Training
Support Model
Post-Migration
Severing UK <> BR link
Stopping data replication
Prod
Next Steps
Deprecate Postrgres / Migrate to Oracle
Application performance
Performance / Latency analysis