C8 PROCESS UNIT TURNAROUND (Activities During Turnaround (Modifying…
C8 PROCESS UNIT TURNAROUND
Definition
to change, upgrade piping and vessels erode and corrode
rotating equipment wears out
Shut down a plant or unit
Reasons
New equipment designed to improve operations
replace obsolete equipment is scheduled for installation
Old or worn out equipment
cause excessive downtime for unscheduled repairs
cause serious problems
Objectives
Complete the TAR at the lowest possible cost
Achieve the best quality of workmanship
Complete the TR in the shortest possible time
Execute the TAR with the highest possible safety record
Activities During Turnaround
Modifying existing equipment
New technology
Based current capacity
Changing the original design
Installing new equipment
Expansion of the plant
increase the plant capacity
Preventative equipment maintenance
changed the commutator brushes in electric motors
replace bearings, rings, and other parts that wear with time
corroded trays in distillation towers
Completing major project work
Testing and inspection
check safety and process interlocks to verify work properly
testing and inspecting pressure relief and safety valve
inspected for corrosion/erosion
Factors affecting rash accident
hurry up and get it done work attitude
contractors are involved-dont know better about the plant
piping and equipment are opened-leak, exposure
fatigue-overtime
Procedure
Entry PV (CS)
gas test the vessel interior for a breathable (oxygen) atmosphere free of flammable or toxic material
permit to enter
air movers must be installed to ventilate the vessel
large PV, the technician must wear a self-contained breathing apparatus
must be purged and blinded
Hot Work
Anything that can generate sufficient heat for combustion
Precautions must be taken
always assumed that equipment will still contain some process materials even though the unit was purged
hot work permit
Blinding
No need for utility lines
prevent the backing of hazardous materials into the unit
must be tagged out
Unit blind list
Evaluation of TR
Was the TAR cost on budget or below budget
Did the actual TAR length meet or exceed the scheduled time objective
Was the TAR involved injuries or accident
Was all the planned TAR activities achieve the target
MOHD ADHAM B KAMARUDDIN