Cost Overrun Clusters (Statutory Cost (Excise Duty, VAT/ CGST, Service…
Cost Overrun Clusters
Statutory Cost
Excise Duty
VAT/ CGST
Service Tax/ SGST
Levies
Cess
PF
Octroi
Labor Cess
ESI
Logistic Constraints
Additional P&M
Material Handling
Reduced Labor Produvtivity
Inter carting Wastage
Stacking wastage
Additional Labor
Maintainance of Approach roads
Reshifting of Temporary Structures
Diminished Productivity
Due to Rain
Due to Heat
Due to Festivals
Due to Design Constraints
Due to Earth conditions/ slush
IDC Overrun
P&M overstay
Support Materials Overstay
Water & Power
Staff Overstay
Resource Idling
Labor Idling
P&M Idling
Formwork Idling
Water & Power
Unenvisaged Activities
Labor
Material
P&M
Staff/ Supervision
Reworks & Rectifications
Labor
Material
P&M
Supervision
Political/ Local Liabilities
Extra cost of Bulk materials
Strikes/ Shutdowns
Liasoning
Escalation
Design Wastage
Working Hour Restrictions
Coordination with other Agencies
C: client, S: subcontractor, G: government, L: localites, V: vendors