Project Management (Technical Risks Management :red_flag: (Process Systems…
Project Management
Technical Risks Management
:red_flag:
Mechanical
CSA
Electrical
ELV/IT/FMS/Security
Process Systems
BCD
Calculations
Who is going to make calculations in Pipe Flow :question:
Yit Kit :check:
Are we going to calculate the whole systems or only "new" parts :question:
Only for new parts :check:
Pipe flow calculation :question:
Based on Frank (Intel) should be provided by us
Source file
Missed :!:
Model (Layouts, sections, etc)
Do we have model :question:
NWD - YES. RVT - No :!:
Tool layout / Sub fab layout :question:
Tool layout still not provided :!:
Existing space management :question:
No information :!:
Do we have available utilities for our systems :question:
GAP analysis for base build utilities should be done by relevant system owners
Consider move-in path and emergency escape ways :red_flag:
Topic for 3D team.
BOM
LL
Identification of LL :red_flag:
Done :check:
Check with Intel what was purchased :red_flag:
Done :check:
Did we get Intel approved suppliers list :question:
Yes, received. :check:
Other
Template for BOM :question:
PFD
Missed source files :!:
PCD
Calculations
Pipe flow calculation :question:
Not required
Model (Layouts, sections, etc)
Do we have model :question:
NWD - YES. RVT - No :!:
Tool layout / Sub fab layout :question:
Tool layout still not provided :!:
Existing space management :question:
No information :!:
Do we have available utilities for our systems :question:
GAP analysis for base build utilities should be done by relevant system owners
Consider move-in path and emergency escape ways :red_flag:
Topic for 3D team.
BOM
LL
Identification of LL :red_flag:
Done :check:
Check with Intel what was purchased :red_flag:
Done :check:
Did we get Intel approved suppliers list :question:
Yes, received. :check:
Other
Template for BOM :question:
WP09 - SG&BG
Drawing
Last received updated layout drawing from intel (LOR4.1 as basis)
Late received schematic drawing from intel
Late received updated tool layout from intel
Late received updated ACAD format layout from Intel
Late received updated BIM model from Intel
Late received latest gas equipment layout from Intel
Long Lead Items
Approved brand list is incomplete
Specifications of Long Lead items is incomplete
Supplier list for Long Leads is incomplete
Interfacing&Scope Specification
Scope boundary determined?
Late OFCI equipment handover by Intel
Shut-down and Tie-in process not approved
Other utilities are not ready on time and are not available within the service area
General
Possibility EOT approved?
Bill of Quantities
Valve and equipment quantity not confirmed
PM Risks Management
:red_flag:
Supplier
Legal
Schedule