Progress (Use of Management stages for control (Technical stages…
Progress
-
-
Purpose
The Purpose of the progress theme is to establish mechanisms to monitor and compare actual achievements against those planned: provide a forecast for the project objectives and the project's continued viability; and control any unacceptable deviations
Two principles of PRINCE2 are managing by stage and continued business justification. the Progress theme provides the mechanisms for monitoring and control, enabling the critical assessment of ongoing viability
The progress theme provides such mechanisms for all management levels ( delivering, managing, directing ) within the project management team and for corporate or programme management outside the project
Another PRINCE2 principle is that projects are managed by exception, setting tolerances for project objectives to establish limits of delegated authority. The Progress theme provides the mechanisms to monitor progress against the allowed tolerances, and the controls to escalate to the next level should any forecast suggest that one or more tolerances will be exceeded
Control of progress is all about decision making and is central to project management, ensuring that the project remain viable against its approved business case
-
-
-