PLAN (Levels of plan (PRINCE2 recommends three level of plan, satisfying…
PLAN
Levels of plan
-
-
PRINCE2 recommends three level of plan, satisfying the needs of the three levels of managment
-
-
-
-
-
-
-
Note also the benefits Review Plan that we looked at earlier it covers corporate project and stage levels
-
Purpose
The purpose of the plans theme is to facilitate communication and control by defining the means of delivering the products ( the where and how, by whom, and estimating the when and how much)
-
-
-
The act of planning helps the project management team to think a head and to mentally "run through" the project
-
-
Exception Plans
-
If approved, the exception plan replaces the project plan or the relevant stage plan
-
-
-
Exception plans are not produced for work packages. if a team manager forecasts that workpackage may exceed tolerances, an issue :star: is raised. if the issue can be resolved within stage tolerance the project manager will update work package or issue a new one.
team plans
-
-
-
Note that in some situations the project manager may not see the detail of a team plan for reasons of confidentiality
Team managers may create their Team plan s for the next stage in parallel with the project manager preparing the stage plan for the next stage
Stage Plans
-
stage plans are similar in content to the project Plan but a stage plan has enough detail for teh project manager to manage the stage on a day to day basis
-
-