Multi-Level Parking (Finishing (5.5 Interior works, 5.6 Toilet fixtures, 5…
Multi-Level Parking
Finishing
5.5 Interior works
5.6 Toilet fixtures
5.7 Lift car installation
5.4 Paint & Wall finishes
5.3 Electrical Fittings
5.2 Floor Finishing
5.1 Plastering
Excavation
1.1 Marking
1.2 Excavation of trench
1.4 Dumping of excavated earth if necessary
1.3 Chemical treatment
RCC Substructure
2.1 Foundation - PCC Bed
2.2 Marking of columns
2.3 Laying of Plinth
2.4 Damp Proof Coating
Superstructure
3.1 RCC Frame Structure
3.2 Brickwork
3.2.1 Partition Walls
3.3 Door & Window Framing
Services
4.1 Plumbing pipelines
4.2 Electrical Trench
Roofing
6.1 Water Proofing
6.2 Other Roof finshes