Sol:
This is similar to the above question, but the sequence is important here.
Assume x = 10, y = 20, z = 40
=> 1st day ---- 1/10
=> 2nd day ---- 1/20
=> 3rd day ---- 1/40
Therefore, in the first 3 days, A, B and C can complete [(1/10) + (1/20) + (1/40)] th of the work
=> In 3 days, 7/40 of the work will be completed.
=> In 3x5 = 15 days, 35/40 part of the work will be completed.
Left out is 5/40 part of the work, A can complete 4/40 in 1 day
=> Left out is 1/40 of the work. B can complete 2/40th work in 1 day
=> B takes half day to complete the remaining 1/40th work
=> Therefore, total time taken = 15 + 1 + 0.5 = 16.5 days
Note: In this kind of questions, sequence of men is very important. That determines the answer.