Chapter 6 (Plan Schedule Management (Process (T&T (Expert Judgment,…
Chapter 6
Plan Schedule Management
Process
-
OUTPUT
Sched mgt plan
Establish criteria & activity for developing, monitoring and controlling sched
-
-
-
-
Develop Schedule
Process
T&T
-
-
Resource optimization
Levelling
-
Smoother distribution of resource, thus resource limited sched
Change original critical path, increase duration
-
-
Smoothing
-
Crit path unchanged, proj. completion not delayed
-
-
Adjust start and finish dates of activities to adjust resource use to be less or equal to resource available
Schedule Compression
-
Crashing
-
-
-
If budget fixed, cannot crash
-
-
-
-
-
-
-