MHI at OTL 14-8-2016 (Future Projects (Confirm Boom details (Boom…
MHI at OTL 14-8-2016 (
Future Projects,
Createc,
Report: Cell Minimisation,
Unit-1 and Unit-2 FS final report meeting.2) Discussion on activities in 2nd Half FY2016 (Oct2016-Mar2017).
(from highest priority) - Unit-1,2 Enclosure interface to X-6 penetration
- Design optimization of boom length and number of articulation for better manoeuvre inside PCV
- VR simulation for avoidance of interference and boom system retrieval in case of break down
- Maintenance of system and detail simulation of recovery from trouble (including arm replacement, additional system for backup)
- Lead time clarification for design and manufacturing (15 months expected) and training plan
- RPV sampling
- Unit-3 Cell design
- Top access assist for side access FDR
,
Dose at X6 port (Unit 1), 1600msv/hr,
Studies 1-5 start 1st,
Nov end by 1st March 17,
Ideas to close the gap between end of studies at end of Feb 2017 till start of design/build at 1st June 2017,
External dose at Air lock/equipment hatch ~ 3msv/hr,
MHI developing 'optical 3D sensor')